Me revoilou,
As discussed below, we just finished two weeks of madness, during which we can say we made good progress.
The final layer of plaster has been capped a week ago. Faster than expected because the bonding layer has dried more quickly than expected.
were fixed cables, past the latest techniques in line for this purpose. I admit it's scary when you see close up the wall permanently. Hopefully we forgotten anything!
The false ceiling of the kitchen is also installed. Remain to dress and paint it.
side insulation was belatedly decided to fill the partition technique with 4 cm Canaflex Wool (hemp). It was tiring but cut easy to install. Flo has virtually isolated the house alone. They came
projecting 6 cm of polyurethane on the ground floor Wednesday and was placed on 7 loops of the heating network ground this weekend. Its super easy to make and the most economical system of all. (I mean if we put ourselves)
Next Step In principle, this week we test the tightness of the house.
Servidiam cuckoo passes to see if everything is ok with the isolation device come before pouring concrete waxed in about ten days.